Park City Mountain Resort, UT, Lift Upgrade Approval Upheld Through Planning Commission

Park City Mountain Resort has won approval to upgrade two key ski lifts after a hearing officer upheld the Planning Commission's decision. The resort plans to replace the Eagle lift with a high-speed six-pack and upgrade the Silverlode Express from a six-pack to an eight-pack. The project has faced years of delays and resident opposition over capacity concerns.
Key points
- Hearing Officer Pack upheld the Planning Commission's lift upgrade approval in July. The decision found that the commission's May 27 approval was supported by substantial evidence and correctly applied Park City Municipal Code.
- Six residents filed an appeal challenging the lift upgrades in June. The appeal argued that the Planning Commission failed to gather sufficient information about the resort's Comfortable Carrying Capacity before granting approval.
- The new Eagle Express lift will increase uphill capacity by 55 percent. The high-speed six-pack will boost hourly capacity from 1,800 to 2,800 guests, with a 5,796-foot span and 1,600-foot vertical rise.
- The Silverlode Express upgrade will boost capacity from 3,000 to 3,600 guests per hour. Pack's research found that "the new upgrades will increase safety and enhance guests' experience at the resort."
- Residents worried that higher capacity lifts would worsen crowding at the resort. PCMR countered that the upgrades were "expected to minimize congestion and reduce wait times across the resort."
- Park City Mountain Resort has pursued these upgrades for more than four years. Residents can still appeal to Utah's Third District Court, though approval now clears the way for construction to proceed.