Ski Bluewood, WA, Announces Delay on New High-Speed Quad Lift

Ski Bluewood in Washington announced it cannot complete its new Skyline Express high-speed quad chairlift before the 2026-27 season due to delayed shipments of critical components from Austria. The resort initially targeted the 2025-26 season but faced a dispute with its lift broker. Construction now begins April 2026, with completion targeted for September or early October 2027.
Key points
- Rope and bullwheels shipments arrived too late for summer 2026 construction. The parts' mid-September arrival missed the resort's limited timeframe to remove the old lift and install the new one, marking the second delay for the Skyline Express project.
- Manager Peter Korfiatis stated the resort must move forward immediately upon spring arrival. He said, "Starting in April, there are no questions asked. It's remove the chairs, cut the rope, and start going."
- The new Skyline Express will be Bluewood's only high-speed bubble quad lift. It will carry 2,400 people per hour and significantly reduce wait times while improving comfort and reliability compared to the existing three-chair lift.
- Bluewood's small size makes this delay particularly impactful for operations. Korfiatis emphasized, "If we don't have a lift, we don't have a season," noting the Skyline Express is the only lift accessing the resort's peak and majority of terrain.
- The resort has completed preliminary construction work during the delay. Crews poured concrete, backfilled towers, and prepared infrastructure so work can begin immediately when remaining components arrive.
- Bluewood is developing mountain biking trails as a year-round attraction. The resort received Forest Service approval and is working with Tamarack Trail Works to create trails providing access to 20-plus miles for all ability levels.