Ski Bluewood's Skyline Express pushed to 2027

Ski Bluewood in southeastern Washington has postponed installation of its long-awaited high-speed chairlift to late 2027, marking the second consecutive season delay. A dispute with lift brokers over shipping costs and currency fluctuations left critical components stranded in Austria for over a year. The resort, which relies on the single aging triple chair for summit access, faces operational challenges that have prevented construction from beginning.
Key points
- Ski Bluewood delayed its Skyline Express quad lift to late 2027. The used 1993 Austrian chairlift's final components—haul rope and bullwheels—were only expected to arrive mid-September, missing the summer construction window needed to replace the existing triple chair.
- A dispute over shipping costs and currency adjustments delayed component delivery. Steelhead Systems claimed shipping expenses rose 70 percent above the original $600,000 estimate and argued the weakening US dollar added further costs, which Bluewood characterized as "inflated and unjustifiable."
- The resort filed suit in British Columbia Supreme Court against brokers and shippers. WGSKI alleged breach of contract and negligent misrepresentation, while Steelhead Systems countersued for unpaid invoices and denied the allegations.
- A judge ordered shipment of remaining containers from Austria to Washington. The ruling unblocked the parts but came too late to meet the 2026 construction deadline.
- The timing is operationally critical for the small resort. General manager Peter Korfiatis stated that "without the Skyline lift there effectively is no season" because the mountain relies on the single aging triple for summit access.
- Foundation and site preparation work is substantially complete. Once the rope and bullwheels arrive and the season ends, installation can proceed quickly, positioning the resort for operation by fall 2027.