Whistler Blackcomb’s New Showcase Chairlift Continues To Take Shape Ahead Of 2026-27 Season

Whistler Blackcomb's new Showcase Chairlift project is advancing toward a 2026-27 opening as crews complete major foundation work on Blackcomb Mountain. Concrete foundations for all lift towers and the bottom terminal have been finished, with the upper terminal already installed. Tower installation using heavy-lift helicopters is expected this fall.
Key points
- All concrete foundations for lift towers have been completed. The resort confirmed that foundation work across all tower locations on Blackcomb Mountain is now finished as construction enters its next phase.
- Upper terminal installation has been completed. The upper station for the Showcase Chairlift is now in place on the mountain.
- Bottom terminal foundation work is done. Additional earthwork around the bottom terminal area is expected to conclude in September.
- Tower installation will require heavy-lift helicopter support. The installation of lift towers represents one of the largest remaining construction phases and is scheduled for fall deployment.
- The fixed-grip quad will improve alpine terrain access. The new chairlift will provide "faster and easier access to terrain on Blackcomb Mountain" once operational.
- Opening is targeted for the 2026-27 winter season. Tower installation is expected to be among the final major construction milestones before the lift moves into testing and operation phases.